TAP: Once construction is completed, the pipeline will be buried underground
Baku, December 11, AZERTAC
Baku, December 11, AZERTAC
Baku, November 28, AZERTAC
The 1,850 kilometers-long Trans Anatolian Natural Gas Pipeline Project (TANAP) and the 878 kilometers-long Trans Adriatic Pipeline project (TAP) were interlinked at the Maritsa River located on the
Baku, October 19, AZERTAC
Under the construction of the Trans Adriatic Pipeline (TAP), land cover at 80% of Greece and Albania`s routes have been completely restored, said TAP AG, the operator of the pipeline.
Baku, August 17, AZERTAC
“97% of pipes (740km out of 765km) have been strung in Greece and Albania,” the Trans Adriatic Pipeline (TAP) AG company said in its Twitter account.
Baku, July 20, AZERTAC
Baku, July 18, AZERTAC
Baku, May 10, AZERTAC
Around 95 percent of the Trans Adriatic Pipeline (TAP) route has been cleared in Greece and Albania, said a message from TAP AG consortium.
Baku, March 28, AZERTAC